G98 or G99 for Home Battery Storage in Great Britain?

Aktualisiert am

Homeowner_and_installer_reviewing_a_home_battery_and_solar_grid-connection_plan_in_a_British_home.

You cannot decide whether G98 or G99 applies to a home battery from its kWh capacity alone. In Great Britain, the installer has to assess the whole grid-connected generating arrangement: what is already connected, how the battery is connected, the aggregate Registered Capacity per phase, the number of units and phases, type-test status, and any agreed export or import limitation scheme.

This guide explains what those checks mean for a homeowner and what to ask before the installation proceeds. The current G98 and G99 Engineering Recommendations discussed here apply in Great Britain; Northern Ireland uses separate G98/NI and G99/NI documents. Check the current ENA catalogue for the Northern Ireland documents.

In short

G98 may apply only when the complete installation meets the relevant G98 conditions, including the aggregate Registered Capacity limit of no more than 16 A per phase and the applicable type-test requirements. If the installation falls outside G98 scope or does not comply with it, the applicable G99 connection process needs to be considered. Existing solar, a separate battery inverter and multiple generating units can therefore change the answer.

If you need the system basics first, see how solar battery storage works before comparing connection routes.

G98 or G99: the short answer

G98 is the Engineering Recommendation for Fully Type Tested micro-generating plant within its scope. The current G98 Issue 2 is scoped to Great Britain, expressly includes electricity storage, and defines a Micro-generating Plant as one or more micro-generators with an aggregate Registered Capacity no greater than 16 A per phase. It also states that the G99 procedures apply to micro-generators greater than 16 A per phase. See the current ENA G98 catalogue entry and scope.

For a homeowner, the practical lesson is simple: do not classify the new battery in isolation. The proposed route depends on the electrical generating arrangement connected to the property, not just the battery label or its stored-energy capacity.

What actually decides the G98 or G99 route?

Before choosing a route, the installer should build a picture of the whole installation. Six inputs matter most: existing generation, inverter topology, aggregate AC generating capacity per phase, the number of units and phases, equipment type-test status, and whether an export or import limitation arrangement is proposed.

  1. Identify any solar PV, battery storage or other generation already connected.
  2. Confirm whether the battery has its own AC inverter or shares conversion equipment with another generator.
  3. Establish the aggregate Registered Capacity and how it is distributed per phase.
  4. Count the generating units and confirm the supply and connection phases.
  5. Check the relevant Fully Type Tested evidence for the intended connection route.
  6. Identify any proposed G100 export or import limitation and confirm how the DNO will treat it.

Start with everything already connected

An existing solar installation can affect the assessment because the relevant generating arrangement may include more than the new battery. Ask the installer to review the existing inverter and any previous DNO connection information rather than treating the battery as a stand-alone addition.

If you already have solar panels, compare AC-coupled battery storage for existing solar systems before finalising the connection design.

Use aggregate AC generating capacity, not battery kWh

Battery capacity in kWh tells you how much energy the battery can store. It does not, by itself, decide G98 or G99. The connection assessment instead looks at the generating arrangement and the relevant AC output or current conditions, including the aggregate Registered Capacity per phase.

Three different numbers that should not be confused
Term Typical unit What it tells you
Battery capacity kWh How much energy can be stored.
AC output / power kW How quickly electrical power can be supplied on the AC side.
Registered Capacity / current Capacity recorded for the generating plant / A per phase A key part of determining whether the complete installation can fall within G98 scope.

Check whether the battery has its own inverter

Topology matters. A battery connected through its own AC inverter can create a different aggregate generating arrangement from a battery that shares a hybrid inverter with solar PV. That is why two homes with batteries of the same kWh capacity may not follow the same connection route.

The safe question is not “What route does this battery use?” but “How is this battery connected alongside everything else at this property, and what is the resulting aggregate capacity per phase?”

Check the number of units and phases

G98 uses an aggregate per-phase concept. Multiple generating units do not each receive a separate 16 A allowance. The installer must consider how the complete plant is arranged and how its Registered Capacity is distributed across the relevant phase or phases.

For that reason, avoid shortcuts such as multiplying a single-phase threshold by the number of phases without checking the actual architecture. The connection arrangement and the relevant engineering requirements still have to be assessed together.

Check the equipment’s type-test status

G98 is for Fully Type Tested micro-generators that meet its requirements. The current ENA G98 scope refers to a Micro-generator Type Test Verification Report demonstrating that the design meets G98. This is a separate question from battery capacity and should be checked for the equipment and intended route. Review the current G98 scope on the ENA catalogue.

Decision_tree_showing_the_checks_that_determine_a_G98_or_G99_home_battery_connection_route_in_Great_Britain

When can G98 apply to a home battery?

G98 can apply where the complete micro-generating plant falls within the current G98 scope and satisfies its requirements. For the domestic decision discussed here, that includes the Fully Type Tested requirement and an aggregate Registered Capacity no greater than 16 A per phase.

Where the applicable G98 procedure is used, it is commonly described as a connect-and-notify route. That should not be read as a promise that every project can proceed without any prior DNO discussion; the installer still needs to confirm the correct procedure for the actual installation.

G98 and G99 at a homeowner decision level
Question G98 G99
Core scope Fully Type Tested micro-generation within G98 conditions Generation outside or non-compliant with G98 scope
Capacity concept Up to and including 16 A per phase, aggregate Registered Capacity Includes installations outside that G98 limit or scope
DNO process Normally connect and notify under the applicable G98 procedure Applicable G99 connection process before connection
Existing generation Must be considered Often becomes important when the combined arrangement leaves G98 scope
G100 Not a synonym for G98 May form part of relevant connection arrangements where limitation is required
Timing No generic promise Depends on the route, DNO and network assessment

When does G99 need to be considered?

G99 needs to be considered when the generating equipment falls outside G98 scope or does not comply with G98. That can include an installation whose aggregate capacity exceeds the G98 limit, but G99 should not be reduced to one universal domestic wattage band.

The applicable G99 connection process is followed before the relevant installation is connected. The exact process and timing depend on the project, the DNO and any required network assessment, so this guide does not give a generic approval timescale or fee.

Why adding a battery to existing solar can change the route

If an existing PV system already has an AC inverter and the new battery introduces another AC power-conversion unit, the assessment may need to consider their outputs together. That is why an installer should review the existing generation as part of the new battery design rather than checking only the new device.

Worked example: 3 kW solar plus a 3 kW battery inverter

MCS MIS 3012:2025 gives a specific example: a 3 kW solar PV system and a 3 kW electrical energy storage system are connected in parallel to the same single-phase AC supply. MCS states that the combined maximum theoretical output is greater than 16 A, so G99 applies in that stated scenario. See MIS 3012:2025 from MCS.

Why the conditions matter: this is a worked example of two 3 kW systems connected in parallel to the same single-phase AC supply. It should not be generalised to every solar-plus-battery topology.

Where does G100 export limitation fit?

G100 is not a third simple power band and it is not a shortcut that automatically turns a G99 installation into G98. The current G100 Issue 2 Amendment 2 sets technical requirements for customer export and import limitation schemes where there is an agreed need to restrict current flow at the connection point or prevent network voltage limits being exceeded. The DNO assesses whether a limitation scheme is suitable for the relevant network circumstances. See the current ENA G100 scope.


Do not treat G100 as a G98 bypass

A G100 limitation can form part of a DNO-agreed connection design, but the applicable G98 or G99 route still depends on the complete installation and the relevant DNO process.

What should your installer do with the DNO?

The Distribution Network Operator (DNO) needs information about the generating arrangement being connected to its network. The installer should therefore establish the existing system and the proposed battery configuration before deciding what notification or connection process applies.

Before installation

  1. Record the existing solar, storage or other generation already connected.
  2. Confirm the proposed inverter arrangement, number of generating units and supply phases.
  3. Work out the relevant aggregate Registered Capacity per phase.
  4. Check the equipment’s type-test evidence for the intended route.
  5. Identify whether a G100 export or import limitation arrangement is part of the design.
  6. State the proposed G98 or G99 route and follow the applicable DNO procedure before the project proceeds to connection where required.

After commissioning

The relevant notification and commissioning paperwork should be completed under the applicable procedure, and the homeowner should keep the DNO correspondence with the installation records. For an MCS installation, MIS 3012:2025 says that notification to the DNO under the relevant G98 or G99 procedure is undertaken by the MCS Contractor. Read the current MCS battery storage standard used for this point.

DNO approval, MCS and SEG are separate

These processes are related, but they do different jobs. MCS certification is not the same as a DNO connection decision, and a G98 or G99 outcome does not itself create a Smart Export Guarantee (SEG) payment.

Three separate questions
Process What it is about What it does not prove
DNO / G98 or G99 The applicable grid-connection procedure for the generating installation It does not by itself prove MCS certification or SEG payment eligibility.
MCS A certification framework with installation standards and contractor duties, including relevant DNO notification duties under MIS 3012 An MCS certificate is not the same thing as a DNO connection decision.
SEG A separate export-payment arrangement administered by SEG licensees A G98 or G99 connection outcome does not itself create an SEG payment.

Ofgem explains that generators who want SEG payments apply to a SEG licensee, which has its own application process and terms. That is separate from deciding the G98 or G99 connection route. See Ofgem’s SEG guidance for generators.

Questions to ask before you accept a battery quote

A good quote should make the connection assumptions visible. You do not need to calculate the route yourself, but you should be able to ask how the installer reached it.

Homeowner quote checklist

Have you included my existing solar, storage or other generation in the assessment?
Does the proposed battery use a separate AC inverter or share a hybrid inverter?
What is the aggregate Registered Capacity per phase for the proposed installation?
How many generating units and phases are being assessed?
What type-test evidence applies to the equipment and proposed route?
Are you proposing G98 or G99, and why?
Is a G100 export or import limitation scheme part of the design?
What will you submit to the DNO, and what documentation will I receive?

Note: The applicable connection route depends on the actual installation and the relevant DNO. This guide explains the framework; it is not a site-specific connection approval.

Keep the installer’s written explanation with the quote so you can compare the assumptions behind the proposed connection route before moving on to product selection.

Have a system-specific question?

Contact Sunpura with details of your existing generation, supply phase and proposed battery configuration. Our team can help with Sunpura system information, but the applicable connection route still depends on the actual installation and the relevant installer/DNO decision.

Contact Sunpura

Once the DNO route and installation requirements are clear, you can compare home battery storage options.

Explore more UK home battery storage guides.

Frequently asked questions

Is a home battery G98 or G99?
It depends on the whole installation, not the battery alone. G98 may apply where the complete plant meets the relevant G98 requirements, including its aggregate capacity and type-test conditions; otherwise the applicable G99 route needs to be considered.

Does the battery’s kWh capacity decide whether I need G98 or G99?
No. kWh describes stored energy. The connection assessment concerns the generating arrangement and the relevant AC capacity or current, including the aggregate Registered Capacity per phase.

What if I already have solar panels?
Existing generation should be included in the assessment. A separate AC-coupled battery inverter can change the aggregate generating arrangement, so the installer should review both the existing solar system and the proposed battery design.

Can G100 export limitation keep a larger battery system under G98?
Not automatically. G100 concerns export or import limitation schemes and may form part of a DNO-agreed connection design. A limitation scheme does not, by itself, convert an otherwise G99 installation into G98.

Who handles the G98 or G99 paperwork?
For an MCS installation, MIS 3012:2025 says the MCS Contractor undertakes the relevant DNO notification under G98 or G99. As the homeowner, confirm the proposed route and keep the DNO documentation with your installation records.

Is MCS certification the same as DNO approval?
No. They are separate processes. An MCS Contractor has duties relating to the relevant DNO connection requirements, but MCS certification is not the same as the DNO connection decision.

Does G98 or G99 mean I can get Smart Export Guarantee payments?
No. SEG is a separate supplier-administered export-payment scheme. A G98 or G99 connection outcome does not itself create an SEG payment.

Do the same G98 and G99 documents apply in Northern Ireland?
No. Northern Ireland has separate G98/NI and G99/NI documents. The Great Britain G98/G99 framework in this guide should not be applied to Northern Ireland as though the documents were identical.


Jason - Sunpura Energy

Written by Jason

Jason is Vice President at Sunpura Energy and leads product and technology strategy. He works on home battery storage, energy management, smart metering and practical ways households can use solar and grid electricity more intelligently. His articles explain technical topics such as battery sizing, off-peak charging, export, retrofit and backup boundaries in clear, practical terms for UK readers.

Zurück zum Blog

Hinterlasse einen Kommentar